Training › Manufacturing and logistics › Lesson 3 of 5
Run a work order on the Production screen
Release a work order, issue its material, book the hours and receive the finished units into stock.
The steps
Find it
- In the menu on the left, under MANUFACTURING, tap Production. On a phone, open the menu with the button at the top left first.
- Work orders is the one list of everything you are building, whether material planning raised it or you did.
Raise and release the work order
- Tap New work order, tick Ergonomic Sit-Stand Desk 1600mm, then tap Raise work order. It starts as planned.
- Tap Search by order number, product or customer, type desk, then tap Release on its row. It is now committed to the floor.
Issue, book and complete
- Tap Search by order number, product or customer, type desk, then tap Open. The order shows its steps, its costs and its lots.
- Tap Issue material. Unless you say how many units to issue for, it picks everything the order still needs.
- Tap Issue. The components move from stock into work in progress at what their batches cost.
- Tap Book labour, tap 7.5 and type 6 for the hours worked, then tap Book labour. Hours add up, so a negative corrects a mistake.
- Tap Complete, check the quantity is the good units you built, then tap Build it. They go into stock at standard cost.
Scenario: see what the job really cost
- Tap Search by order number, product or customer, type desk, then tap Open on the finished order.
- Tap Costing & variances to compare what the job cost with its standard. The difference is posted to the variance accounts.
Scenario: the customer cancels the job
- Tap Search by order number, product or customer, type WO-0001, then tap Open.
- Tap Cancel order. Anything already issued or booked is written off to Manufacturing Scrap / WIP Write-off, and issued material does not go back on the shelf.
- Tap Cancel the work order. There is no undo, which is why Ledgr asks first.
More detail is in the guide.
Check yourself
What happens when you release a work order?
- The finished units are received into stock
- It is committed to the floor and the routing's steps are copied onto it
- The components are bought from your supplier
Show the answer
It is committed to the floor and the routing's steps are copied onto it
A customer cancels a job that already had material issued to it. What happens to that material?
- It goes back on the shelf
- It is written off to Manufacturing Scrap / WIP Write-off and does not return to stock
- It stays in work in progress until the next job
Show the answer
It is written off to Manufacturing Scrap / WIP Write-off and does not return to stock
You book 4 hours on a step, then another 3 hours. What is booked?
- 7 hours, because hours add to the running total
- 3 hours, because the second booking replaces the first
- 4 hours, because a step takes one booking only
Show the answer
7 hours, because hours add to the running total